Undertake a procurement exercise for the demolition of a HORSA unit and replacement with a double prefabricated classroom unit at Boroughbridge Primary School.
REPORT TO; The Assistant Director, Commercial, Property and Procurement
DECISION DATE: 30th January 2024
PROPOSED RECOMMENDATION
To undertake a procurement exercise for the demolition of a HORSA unit and replacement with a double prefabricated classroom unit at Boroughbridge Primary School.
BACKGROUND TO SUPPORT THE RECOMMENDATION
The scheme forms part of the CYPS Basic Need Programme.
A competitiveprocurement exercise will be undertaken between February and March 2024. The scheme is programmed to commence on site in July 2024 and is due to complete September 2024.
LEGAL AND GOVERNANCE COMPLIANCE
This is a key decision. The proposal to procure was entered on the forward plan in December 2023.
The procurement exercise will be undertaken in accordance with the Council’s Procurement and Contract Procedure Rules and the Public Contracts Regulations 2015
RECOMMENDATION
That a procurement exercise be progressed for the project at Boroughbridge Primary School.
PAMc/KM
Boroughbroidge Proc
30th January 2024